Staff have been busy over the last week attending meetings and moving items to begin our preparations for our September return.
The orders are arriving, full of new resources for our children.
The builders are now at stage 2 of the finishing programme, with floors and the air conditioning units going in. The services are being linked to our new temporary school and everything is going to plan. Stage 3 will be a close inspection to create a snagging list. The final stage will be a big clean - inside and out!
I had a site meeting last week to have a tour of the premises to see how much work has been completed. It looks fantastic so far - still work to do but we will get there!